Home News Citing Non-performance: FG Terminates Obajana-Benin Road Contracts with RCC, Dantata, Mothercat

Citing Non-performance: FG Terminates Obajana-Benin Road Contracts with RCC, Dantata, Mothercat

by Editor
99 views

The Federal Government of Nigeria has terminated the Obajana-Benin Road contracts with three companies- Mothercat Ltd, Dantata & Sawoe Construction Ltd and RCC Ltd, citing non-performance by the firms.

The Federal Ministry of Works, in a statement signed by its spokesperson, Uchenna Orji, listed the ended contract numbers as: 6136, 6137, and 6138.

According to the statement, the projects affected by the termination are the dualisation of Obajana-Benin road, section II (Okene-Auchi) in Kogi/Edo State; the dualisation of Obajana-Benin road, section III (Auchi-Ehor) in Edo State and the dualisation of Obajana-Benin road section IV (Ehor-Benin) also in Edo State.

Dave Umuahia, Minister of Works, noted that the termination of the said contracts became neccessary in view of the inordinate delay of the affected companies in job performance”.

The statement noted that”failure, neglect and or refusal to fulfill their contractual obligations as required by the Standard Conditions of Contract and this has affected the timely completion of the projects and thus resulted in the expiration of the contracts by effluxion of time”.

Umahi said the projects awarded on December 3, 2012 were advertently abandoned by the contractors and no genuine commitment or good faith was shown towards executing the projects thereby exposing road users to untold hardship due to the deplorable condition of the projects.

He, consequently directed “the engineers in charge to take necessary steps to enter upon both the site and the works and take the same over from the affected companies”.

The minister directed the engineers concerned to, upon doing the needful, arrange with the affected companies for a joint measurement of work so far done by the said companies preparatory to taking over the sites from them.

He warned that the ministry under his watch won’t condone acts of unseriousnes and sabotage by contractors whose plan is to become a clog in the wheel of progress of the current administration. He vowed that the government won’t hesitate in terminating all projects that are funded but are non-performing.

Leave a Comment